Joseph J. Albanese, Inc. Successfully Performed Structural Excavation and Construction
of a Huge Data Center During the Rainy Winter Season
Utilizing detailed planning, virtual construction and relentlessly deliberate concrete placement, the Joseph J. Albanese, Inc. team placed approximately 17,000 cubic yards of concrete. Safety precautions included installing rat slab at all excavations to prevent cave-ins as well as stabilization at the bottom of the excavations based on the ground water level. Getting it done, safely.



“Our crews are very skilled at what they do. We put our best foot forward, and we get it done in the safest way possible.”
— Mike Keeth, Project Manager, Joseph J. Albanese, Inc.
"At Joseph J. Albanese, Inc. we are committed to getting the job done safely with relentless and deliberate execution. Our team is devoted in bringing the highest level of quality to every project we do for our clients."
Data Center
Santa Clara, California
Client: Holder Construction Company
Services:
Highlights:
-
Performed structural excavation during the rainy winter season, including stabilization of the bottom of excavations based on ground water level
-
Poured approximately 17,000 cubic yards of concrete
-
Proposed and executed an effective solution that included installing a rat slab at all excavations to prevent cave-ins and safety hazards.
-
Ensured that all slabs met specified FF/FL tolerance
-
Installed 340 anchor bolts correctly and within tolerance
-
Implemented detailed planning to ensure each step of construction was handled with quality and excellence
-
Developed a solid working relationship with the general contractor team to cover multiple scopes of the project
-
Facilitated excellent communication with the General Contractor and field teams
-
Provided a single source for multiple capabilities
-
Delivered solid pre-construction planning to ensure smooth execution
-
Utilized Virtual Construction to digitally build the project prior to construction