Cityline Block, Downtown Sunnyvale

Downtown Sunnyvale Revitalization From Demolition to Site Concrete
Joseph J. Albanese, Inc. has decades of experience building structures that revitalize communities. For the Cityline Block in Downtown Sunnyvale, our team helped make this new, modern live-work community a reality.


“Despite an unusually cold, wet winter, our concrete crews delivered extensive concrete work with intricate finishes on time. Our clients know they can count on us to get the job done right every time.”
— Brandon Maack, Sr. Project Manager
Joseph J. Albanese Family Holdings, Inc.
At Joseph J. Albanese, Inc., we are committed to getting the job done safely with relentless and deliberate execution. Our team is devoted to bringing the highest level of quality to every project we do for our clients.
Cityline Block, Downtown Sunnyvale
Sunnyvale, California
Client:
Devcon Construction
Services:
Performed Demolition of original concrete to prep the site
Facilitated Site Concrete for walls, curbs and sidewalks
Delivered Grading & Paving, including paver installation
Implemented road signage and striping
Facilitated traffic control plans to ensure traffic flow
Coordinated construction around underground utilities to ensure safety without disruption
Highlights:
Facilitated extensive preplanning, including shop drawings and layout plans for the walls and trench drain to ensure all elements came together smoothly
Built the project while working from a podium over a parking garage
Ensured smooth communication by providing RFI’s to the design team
Worked closely with the City of Sunnyvale, the Devcon team and other trades for successful project flow, including weekly coordination meetings
Construction Included:
Grading & Paving
15,000 SF of AC demo and replacement
750 CY of rough grade/flat work excavation
40,000 SF of flatwork grading
20,000 SF of roadway grading
1,200 TN of imported rock over podium concrete
700 TN of AC Paving
Concrete Construction
500 LF of curbs on structure
3,100 LF of curbs on grade
24,000 SF of city sidewalks
56,000 SF of protection slabs over waterproofing
15,000 SF of vehicular concrete
1500 LF of site walls
90 TN of rebar installed for flatwork and walls
500 LF of trench drain installed
4,000 LF of sawcut joints