AC Marriott Hotel

Constructing the AC Marriott Hotel,
the First in Downtown Billings in 45 Years
For the new AC Marriott Hotel, the first hotel to be built in downtown Billings in 45 years, our team safely provided structural and site concrete services, including footings and pier caps, stem walls for the foundations, slab on grade and slab on metal deck.
Soon-to-be one of the tallest buildings in the city, the hotel’s construction site embodies a quarter of a city block in the busy downtown, with very little space for storing materials on-site. On-time deliveries and coordination with on-site subs for materials handling is key to success.


“Everyone on this job has a team mentality, with safety as the Number 1 priority. Planning ahead, constant communication and tight coordination help ensure that the whole team is on top of its game.”
— Logan McIsaac, Project Manager
Allied Concrete, A Joseph J. Albanese Company
At Allied Concrete, A Joseph J. Albanese Company, we are committed to getting the job done safely with relentless and deliberate execution. Our team is devoted to bringing the highest level of quality to every project we do for our clients.
AC Marriott Hotel
Billings, Montana
Client:
Jones Construction
Services:
Highlights:
Placed more than 300 cubic yards of foundations
Installed 14,000 square feet of slab on grade
Positioned 72,000 square feet of slab on metal deck
Constructed foundation footings, pier caps and stem walls
Utilized strategic formwork to reduce setting and stripping time
Planned formwork individually for each structural element
Coordinated to ensure on-time material deliveries of materials
Leveraged preconstruction planning with General Contractor to mitigate risk
Scaled field manpower and leadership to meet critical deadlines