Mass Excavation for the 8.3-Acre ELCO Yards Work-Live Complex

For the new 8.3-acre ELCO Yards complex in Redwood City, our team performed a mass excavation and extensive multi-scope construction capabilities from a single source.

ELCO Yards
Play Video
Brandon Maack, Project Manager

During the wettest year in recent history, our team performed a mass excavation on a huge site, including pumping water out and providing soil stabilization services. Our team expertly perform huge excavations while getting the job done safely.

— Brandon Maack, Project Manager, Joseph J. Albanese, Inc.

At Joseph J. Albanese, Inc., we are committed to getting the job done safely with relentless and deliberate execution. Our team is devoted to bringing the highest level of quality to every project we do for our clients.

ELCO Yards Work-Life Complex
Redwood City, California

Client: Devcon Construction 

Services: 

 

  • Performed mass Excavation for an immense work-life complex encompassing 592,000 square feet of office space, 500 residences and retail/dining space

  • Provided water pumping services to deal with high-groundwater issues 

  • Implemented soil stabilization services to ensure site stability

  • Will perform Structural Concrete and Site Concrete services as the project progresses


Highlights:

 

  • Worked carefully around the recently uncovered Native American archeological site to ensure careful removal of artifacts

  • Delivered exceptional coordination with the general contractor and subcontractors

  • Provided solid pre-construction planning to ensure smooth execution

  • Ensured that all equipment was on-site and on-time despite weather issues 

  • Provided cement treatment to stabilize soil and keep the job moving

  • Provided a single source for multiple capabilities

 

 