St. Vincent Hospital

Intermountain Health’s St. Vincent Regional Hospital

Joseph J Albanese Dog Logo

Constructing a New Regional Hospital in Billings,
Hitting Critical Milestones Before Winter Weather

For the new St. Vincent Hospital, a ground-up build in the busy Billings metropolitan center, our team safely provided structural and site concrete. Working on a tight deadline before the winter weather, we placed more than 2,500 cubic yards of foundations, 100,000 square feet of slab on grade and 700,000 square feet slab on metal deck as well as exterior site work.

“We personally take a lot of pride in helping build St. Vincent Hospital, especially because it will be used by our families, friends and neighbors. Getting it done safely is always key to our success.”

— Logan McIsaac, Project Manager

Allied Concrete, A Joseph J. Albanese Company

At Allied Concrete, A Joseph J. Albanese Company, we are committed to getting the job done safely with relentless and deliberate execution. Our team is devoted to bringing the highest level of quality to every project we do for our clients.

St. Vincent Hospital

Billings, Montana

Client: 

Layton Construction

Services:

Highlights:

  • Placed 2,500 cubic yards of foundations

  • Installed100,000 square feet of slab on grade

  • Positioned 700,000 square feet of slab on metal deck

  • Implemented exterior site work, including retaining walls

  • Met all City of Billings’ requirements, including level ground compliance

  • Worked closely with the General Contractor and subcontractors to meet schedules

  • Leveraged detailed preconstruction planning to mitigate risk

  • Scaled field manpower and leadership to meet critical deadlines